Time and Work
Work refers to any job or task completed over a period of time. The Time & Work concept deals with calculating the time required to complete a job or the work done in a given time by one or more workers.
Basic Relation:
Where rate is the amount of work done per unit time (e.g., per day, per hour).
Alternatively,
Key Idea:
If a person can complete a job in 10 days, then their work rate is of the job per day.
2. Key Formulas & Shortcuts
One Person:
- If A can finish a job in x days, A’s 1 day work is
Multiple People Working Together:
-
If A and B can do a work in x and y days respectively:
-
Time to finish the work together:
Work & Efficiency:
If A is twice as efficient as B, then:
- A’s rate = 2 units/day, B’s = 1 unit/day
- A does the same work in half the time B takes
Alternate Work:
If A and B work on alternate days:
- Total work is done based on summing work done on individual days
- Use LCM of days taken to find total work when needed
Pipes & Cisterns Analogy (Preview):
- Inlets: positive work rate
- Outlets: negative work rate
3. Conceptual Tips & Common Mistakes
- LCM Trick: When multiple people are involved, assume total work = LCM of their individual times. It simplifies calculations.
- Efficiency vs Days: Efficiency ∝ 1 / Time. If A is 25% more efficient than B, A takes 20% less time.
- Beware of “work left” phrasing: Don’t assume what “remaining work” means—clarify with fractions.
- Alternating workdays: Start carefully with Day 1 and alternate manually if needed.
4. Visual Explanation
Example: Work Timeline
Let’s say:
- A finishes a job in 5 days → work/day
- B in 10 days →
Combined rate:
→ They’ll finish 3/10 of the work per day.
So, entire work will take days.
This can be visualized using a stacked bar showing how much each person contributes per day until 1 unit of work is complete.
5. Solved Examples
Example 1: Basic One Worker
Q: A can do a work in 12 days. How much work does A do in 4 days?
A:
A’s 1-day work =
In 4 days:
Example 2: Two Workers Together
Q: A can do a job in 20 days, B in 30 days. Working together, how many days will they take?
A:
LCM of 20 and 30 = 60 (Total work)
A’s 1 day work = , B’s =
Combined = 5 units/day
Example 3: One Starts, Another Joins
Q: A can complete work in 10 days. B in 20 days. A works alone for 2 days, then B joins. How many days in total to finish?
A:
A’s 1 day work = , B’s =
Work in 2 days =
Remaining =
Combined rate =
Time =
Total time = days