A and B together can complete a piece of work in 24 days. C's efficiency is half that of A's. If A, B, and C all work together, they finish the work in 20 days. How many days will B and C take to complete the work if they work together?

Options

A.

45 days

B.

42 days

C.

30 days

D.

48 days

E.

44 days

work and timeefficiencyratioalgebra