A, B, and C together can complete a work in 4 days, while B alone can finish the same work in 24 days. If the efficiency of C is 300% more than that o...
Question
A, B, and C together can complete a work in 4 days, while B alone can finish the same work in 24 days. If the efficiency of C is 300% more than that of B, what is the difference between the number of days taken by A and C to complete the work individually?