A can do a task in 18 days, B can do the same task in 24 days, and C can destroy the whole work in 36 days. If A & B work for the first x x x days...
Question
A can do a task in 18 days, B can do the same task in 24 days, and C can destroy the whole work in 36 days. If A & B work for the first days together, after that C also joined them, remaining work is completed in days. Find how many days all three worked together?