B is 20% more efficient than A. If B is 60% more efficient than A, then B could complete the work in 18 days less than the number of days taken by A. ...

Question

B is 20% more efficient than A. If B is 60% more efficient than A, then B could complete the work in 18 days less than the number of days taken by A. What fraction of work would be left after 12 days, if A and B work together?

Options

A.

15\frac{1}{5}

B.

720\frac{7}{20}

C.

1120\frac{11}{20}

D.

1320\frac{13}{20}

E.

920\frac{9}{20}

workefficiencytimeratiofraction