The table below shows the number of workers and days required to complete three different projects under two different cases: Project Case 1: Number o...

Question

The table below shows the number of workers and days required to complete three different projects under two different cases:

ProjectCase 1: Number of workersCase 1: Days requiredCase 2: Number of workersCase 2: Days required
AXX88X+8X + 866
BYYY1Y - 1Y+6Y + 6Y6Y - 6
CZ2Z^275M2M^2108

If a new team P has a total number of workers equal to 0.5Z×2M0.5Z \times 2M, what is the number of days required by team P to complete project C?

Options

A.

75 days

B.

60 days

C.

90 days

D.

80 days

work and timedata interpretationalgebraproject management