The table below shows the number of workers and days required to complete three different projects under two different cases: Project Case 1: Number o...
Question
The table below shows the number of workers and days required to complete three different projects under two different cases:
| Project | Case 1: Number of workers | Case 1: Days required | Case 2: Number of workers | Case 2: Days required |
|---|---|---|---|---|
| A | 88 | 66 | ||
| B | ||||
| C | 75 | 108 |
If a new team P has a total number of workers equal to , what is the number of days required by team P to complete project C?