Question
The table below shows the number of workers and days required to complete three different projects under two cases:
| Project | Case 1: Number of workers | Case 1: Days required | Case 2: Number of workers | Case 2: Days required |
|---|---|---|---|---|
| A | 88 | 66 | ||
| B | ||||
| C | 75 | 108 |
If 64 workers are assigned to Project A, how many days will it take to complete the work?