A, B, C, D and E are five persons employed to complete a job X. Line graph shows the data regarding the time taken by these five persons to complete t...

Question

A, B, C, D and E are five persons
employed to complete a job X. Line graph shows the data
regarding the time taken by these five persons to complete
the job X individually. Table shows the actual time for
which every one of them worked on the job X.

image.png

PersonDays Worked
A2
B?
C3
D?
E2

Note 1: All persons worked for whole number of days.

Note 2: Jobs Y and Z are similar to job X and require the same amount of effort as job X.
If A, C, and E worked on job Z for 2 days each, and the remaining work was completed by B and D, and the ratio of the number of days B and D worked is 20 : 21, then find the number of days B worked.

Options

A.

50 days

B.

4\frac{1}{2} days

C.

5\frac{1}{2} days

D.

4 days

E.

None of these

work and timeratiodata interpretationtime calculation

Solve This Question

Get instant feedback with detailed step-by-step solution

Start Solving →