A team of workers with identical efficiency can finish a project in 4 days. However, every second day starting from day 2, three workers leave the tea...

Question

A team of workers with identical efficiency can finish a project in 4 days. However, every second day starting from day 2, three workers leave the team, and every second day starting from day 3, two workers join the team. If the project now takes 7 days to complete, determine how many workers were initially part of the team.

Options

A.

4

B.

5

C.

6

D.

8

variable workforceefficiency calculationtime & work