Six men can complete a task in 12 days, eight women can finish the same task in 18 days, and eighteen children can complete it in 10 days. Four men, t...

Question

Six men can complete a task in 12 days, eight women can finish the same task in 18 days, and eighteen children can complete it in 10 days. Four men, twelve women, and twenty children work together for two days. If the remaining work is to be completed by men alone in one day, how many men will be required?

Options

A.

36

B.

24

C.

18

D.

Cannot be determined

rbi officer gr. ‘b’ (phase-1) online exam, 2015work efficiencycombined workremaining work