A can do a work in 12 days. B’s efficiency to do the work is 50% more than that of A. In how many days will B be able to do the work?

Question

A can do a work in 12 days. B’s efficiency to do the work is 50% more than that of A. In how many days will B be able to do the work?

Options

A.

8

B.

10

C.

5

D.

11