Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do 1/4 of the job working together?
Question
Aman can do 50% of the job in 16 days, and Bhanu can do 25% of the job in 24 days. In how many days can they do 1/4 of the job working together?